Concrete Repair Solutions were appointed by a main contractor to carry out a concrete condition survey and intrusive structural investigation at a residential estate in Carmarthen town centre, West Wales.

The estate’s three and four storey blocks are reached by elevated concrete walkways, stairs and a ramp, and the ramp serving the block we surveyed was propped with structural scaffold. Our team inspected and tested the walkway decks, stairs and ramp, and opened up the supporting brickwork to show exactly how the slabs bear on the walls.

All site works were completed in a single day on the occupied estate, and our full report was issued one week later.

What we did

Visual & Hammer-Tap Survey

Inspected the walkway decks, stairs, ramp, soffits and beams
Hammer-tap survey to find hollow and loose concrete
Recorded every defect by photograph and location

Concrete Testing

Cover meter survey
Carbonation depth testing
Concrete dust samples for chloride analysis by a UKAS-accredited laboratory
Schmidt hammer testing

Opening-Up Works

Removed brickwork at slab bearing locations
Recorded each bearing and how it sits against the inner leaf
Reinstated the brickwork at every location

Report & Repair Schedule

53-page photographic report with record drawings
Clear findings on the cause of the deterioration
Schedule of repair works and bill of quantities

Technical overview

The walkways showed spalling, cracking and exposed, corroding reinforcement to the soffits and beams, along with water getting through the decks and corroding handrail fixings.

Testing to British Standards confirmed the cause and extent of the deterioration, giving the engineer accredited results to work from.

The opening-up works exposed how the walkway and ramp slabs actually bear on the masonry, giving the structural engineer measured, photographed evidence to appraise rather than assumptions.

Our report brings all of this together with record drawings, a plain explanation of the cause of the deterioration and a schedule of repair works with a bill of quantities covering concrete repairs, protective coatings, deck waterproofing and repairs around the handrail fixings.

Project challenges

  • Working on an occupied estate around residents' daily access
  • Opening up load-bearing brickwork carefully and reinstating it the same day
  • Testing around a ramp propped with structural scaffold
  • Completing every survey, test and opening-up location in a single day

The outcome

All site works were completed on 12 November 2026 and the investigation report was issued on 19 November 2026.

The client now has a clear picture of the structure: what is wrong, why it is happening and what is needed to put it right, backed by accredited test results and record drawings the structural engineer can work from.

With a schedule of repair works and bill of quantities included, the report gives a direct route from survey to repair.

Services demonstrated

  • Concrete condition surveys
  • Structural investigations and opening-up works
  • Cover, carbonation and chloride testing
  • Schmidt hammer testing
  • Record drawings and photographic reporting
  • Repair schedules and bills of quantities