Written by

Will Hepke is the Director of Concrete Repair Solutions Ltd (CRS), a UK specialist concrete repair and structural refurbishment contractor operating nationally. CRS delivers concrete condition surveys, structural investigations, concrete repair, cathodic protection, protective coatings, façade refurbishment and related specialist works across residential, commercial, infrastructure and heritage assets.

Date

12 November 2026

A structural engineer can only assess what they can see. Drawings for older buildings are often missing, incomplete or wrong, and the details that matter most (slab bearings, beam to column connections, embedded steelwork, lintels and wall ties) are usually hidden behind brickwork, cladding or finishes. Before an engineer can sign off a building, design a repair or confirm a load path, someone has to open the building up safely, test the concrete, and put everything back. That is the job of opening-up works.

This article explains what opening-up works involve, what engineers typically need exposing, how the work is planned and controlled on an occupied site, and what the engineer receives at the end of it.

What are opening-up works and intrusive investigations?

Opening-up works (also called intrusive investigation or exploratory works) are the physical works that let an engineer inspect concealed parts of a structure. They are carried out by a contractor, under the direction of the engineer, at locations the engineer selects.

A typical package combines three things: carefully removing brickwork, cladding or finishes to expose the element in question; testing the concrete and reinforcement at and around the opening; and making good afterwards so the building is left weathertight, safe and as close to its original appearance as possible.

The contractor’s role is to expose, test and record. The engineer inspects each opening, interprets the findings and draws the structural conclusions. Keeping those roles clear protects both parties and keeps the investigation focused on what the engineer actually needs to know.

What do engineers typically need exposing?

The scope depends on the building and the question being asked, but common requests include:

  • Slab and beam bearings concealed behind the outer leaf of brickwork, to confirm bearing length, condition and any corrosion at the support
  • Beam to column and frame connections in concrete-framed buildings
  • Embedded steelwork in early twentieth century steel-framed buildings, where corrosion of the frame can crack the surrounding masonry (often called Regent Street disease)
  • Lintels, nibs and shelf angles supporting brick or concrete facades
  • Wall ties and cavity condition, inspected through a removed brick or with a borescope through a small drilled hole
  • Bearings of precast units and planks, including suspected RAAC, where bearing length is a critical safety question
  • Reinforcement size, spacing and cover at locations where the engineer needs to check capacity
Corroded steel post exposed at its concrete base after opening-up works
A corroded steel post exposed at its base, hidden behind brickwork until opened up

Which tests are carried out alongside the openings?

Opening up a building is disruptive, so it makes sense to gather as much information as possible from each visit. Concrete testing is normally carried out at the same time, at locations agreed with the engineer:

  • Visual inspection and hammer tap survey of accessible concrete, recorded on plan and photographed
  • Cover meter survey to locate reinforcement and measure cover depth (BS 1881-204)
  • Rebound hammer testing to assess the surface hardness and uniformity of the concrete (BS EN 12504-2). Rebound values are not a direct measure of strength unless correlated with cores (BS EN 13791)
  • Carbonation depth testing on freshly broken or cored concrete using phenolphthalein indicator (BS EN 14630)
  • Drilled dust samples taken at increasing depths for chloride analysis at a UKAS-accredited laboratory (BS 1881-124), giving a chloride profile from the surface to beyond the reinforcement
  • Where required, core extraction for compressive strength testing (BS EN 12504-1), petrographic examination (for example to check for alkali silica reaction), and half-cell potential surveys to map corrosion risk

Comparing carbonation depth and the chloride content at reinforcement depth with the measured cover tells the engineer whether the reinforcement is at risk of corrosion, not just whether it is corroding today.

How are opening-up works planned?

Good investigation work is mostly planning. Before anything is removed, the following should be in place:

  • Agreed locations. The engineer selects the openings and test points, and the contractor marks them on plan and on site. Locations are checked against lintels, openings, temporary works and services before they are confirmed.
  • Asbestos information. An asbestos management survey is not enough for intrusive work. A refurbishment and demolition survey (HSE guidance HSG264) covering every opening and test location must be in place and checked before any intrusive work starts.
  • Services scanning. Every hole and opening is scanned with a cover meter and cable avoidance tool, and moved if services are found.
  • Structural stability. Openings are kept small, taken one at a time and never allowed to undermine the masonry above. Where an opening could affect stability, temporary works are designed, installed and signed off before any load-bearing material is removed (see below).
  • Hold points. Clear hold points for the engineer to agree locations, inspect each opening and accept the reinstatement, written into the method statement.
  • Access and the public. Towers, MEWPs or scaffold as needed, with small barriered work areas so residents, staff or the public can keep using the building.

Temporary works: design, installation and sign-off

Many openings can be kept small enough to need no temporary support. Where a larger opening is needed, for example at a bearing, a connection or a section of loadbearing masonry, the structure must be supported before anything is removed. Temporary works on an investigation are managed in the same way as on any construction project, following BS 5975:

  • Coordination. A temporary works coordinator is appointed to manage the process, keep the temporary works register and make sure nothing is loaded or removed until it has been checked.
  • Design brief. The brief sets out the opening sizes, the loads to be carried, the bearing conditions and any constraints from the building or its occupants, based on the information the engineer and the drawings provide.
  • Design and design check. The temporary works, typically props, needles or spreader beams, are designed by a competent temporary works designer and independently checked to the category the risk requires.
  • Installation. The temporary works are installed to the design, with any props bearing onto a structure confirmed as able to carry the load.
  • Inspection and permit to load. The installation is inspected against the design and a permit to load is issued before any loadbearing material is removed.
  • Monitoring and permit to strike. The temporary works are checked throughout the investigation and are only removed under a permit to strike, once the opening has been reinstated and the permanent structure can carry the load again.

Providing the temporary works alongside the opening-up and testing means a single contractor is responsible for keeping the structure stable from the first brick removed to the last one reinstated.

What happens on site?

A typical sequence for a bearing investigation behind brickwork looks like this. The engineer and contractor walk the building and confirm the locations. Non-destructive testing (cover meter, rebound hammer) is completed first, followed by drilling for carbonation and chloride samples. The outer leaf brickwork is then removed by hand at each bearing, with the bricks set aside for reuse. The engineer inspects and records each opening while it is exposed, and any unexpected findings (corrosion, short bearings, missing ties or signs of movement) are reported straight away.

Where an opening must stay exposed overnight, it is covered against the weather, barriered and checked at the end of the day and before work restarts. On occupied buildings, dust is controlled with on-tool extraction, noisy work is kept to agreed hours and walkways, entrances and escape routes are kept clear throughout.

Making good

Reinstatement is part of the investigation, not an afterthought. Removed bricks are rebedded once the engineer has finished, in a mortar matched to the existing in colour and compatible in strength, so it is never stronger than the surrounding brickwork (lime-based where the original is lime). Any cavity trays, damp-proof courses, weep vents, wall ties and cavity barriers or fire stopping disturbed by the opening are reinstated. Test holes and cores are filled with a cementitious repair mortar and finished to suit the surrounding surface. A well-executed reinstatement leaves no visible trace and no new route for water or fire through the structure.

Where the openings reveal defects that need repair, the reinstatement can be held until the engineer’s recommendations are known, so the opening can be used for the repair rather than being reinstated and opened up again.

What does the engineer receive?

The output of an opening-up package should give the engineer everything they need to complete their assessment without a second visit:

  • A marked-up plan of every opening and test location
  • A full photographic record of each location before, during and after
  • Measured cover, carbonation depths and rebound values, with laboratory results for chloride and any core testing
  • Factual observations from each opening (bearing length, condition of concrete and steel, presence of corrosion, voids or cracking)
  • Confirmation that every location has been reinstated and left safe

Structural conclusions and the design of any remedial works remain with the engineer. The contractor’s job is to make sure the evidence behind those conclusions is complete, accurate and well recorded.

Choosing a contractor for opening-up works

Opening-up works sit between surveying and construction, and they need a contractor who understands both. Look for a team that can carry out the testing as well as the builders’ work, can provide and manage any temporary works, works safely on occupied sites, follows the engineer’s direction through hold points, and can also deliver the concrete repairs or strengthening that may follow. Using one contractor for the investigation and the repair means the people who opened up the building already know it when the remedial works start.

Frequently asked questions

Who decides where the openings go?

The structural engineer. The contractor marks the agreed locations on plan and on site, checks them for services, asbestos and stability, and raises any location that cannot be opened safely so the engineer can choose an alternative.

Can the building stay occupied during opening-up works?

Usually, yes. Work is carried out in small barriered areas, one location at a time, with dust extraction, agreed working hours and entrances, walkways and escape routes kept open throughout.

Do opening-up works need temporary works?

Not always. Small openings in non-loadbearing cladding often need none. Larger openings, or any opening in loadbearing masonry or at a bearing, need temporary works designed, checked and signed off under BS 5975 before work starts.

How long do opening-up works take?

A typical package of a handful of openings with associated concrete testing takes one to two days on site, with openings left covered overnight while the engineer inspects them. Laboratory results for chloride and core testing follow afterwards.

Can the same contractor carry out the repairs?

Yes. Where the investigation finds defects, the contractor who opened up the building can deliver the repairs to the engineer’s specification, and openings can be left for the repair rather than reinstated and opened again.

Closing

An engineer’s assessment is only as good as the information behind it. Well-planned opening-up works give engineers direct sight of the details that matter, backed by recognised concrete tests, while keeping the building safe, occupied and weathertight.

CRS carries out opening-up works, temporary works, concrete testing and making good for structural engineers across the UK, as part of our structural investigation service. If you have a building that needs opening up, get in touch with the CRS team.

Related services

Discuss your project

Contact us for a professional consultation and detailed quote

Contact us Call us

Request a survey

Contact us for a professional consultation and detailed quote

Contact us Call us

Get your quote today

Contact us for a professional consultation and detailed quote

Contact us Call us